PART
1 – GENERAL
1.01 DESCRIPTION
A. The information herein details a low profile
cushioned system comprised of two layers of
plywood crossed, and fastened together with
AirTech 7/16” (11mm) natural rubber performance
pads affixed to the bottom and maple strip
flooring nailed to the top.
B. The general contractor shall provide a level,
steel troweled slab to a tolerance of + or -
1/8" (3mm) in a 10'0" (3m) radius and subject to
the approval of the wood floor contractor.
Moisture barriers must be adequate for
conditions. The concrete slab is to be depressed
2- 1/8" (54mm) for 25/32” flooring (20mm).
1.02 QUALITY ASSURANCE
A. All system component parts must be supplied
by Action Floor Systems, LLC.
B. The flooring contractor must be approved by
Action Floor Systems, LLC.
C. Flooring materials must be allowed to
acclimate to building conditions on the jobsite
in a dry, well-ventilated area, not in contact
with masonry, and shall be installed at a
moisture content not to exceed 8% except in
areas of constant high humidity where the
moisture content of the flooring shall not
exceed 10%.
1.03 WORKING CONDITIONS
A. The wood flooring shall not be installed
until all masonry, plastering, tile, marble and
terrazzo work is completed, and overhead
mechanical trades and painters have finished in
wood floor area. The building must be reasonably
dry; all openings must be closed in; permanent
heating and air conditioning installed and
operating.
B. The subfloor shall be dry, free of foreign
materials, and turned over to the wood flooring
contractor broom clean. Moderate room
temperature of 65-degrees (F) 18 degrees (C) or
more shall be maintained a week preceding and
throughout the duration of the work. Humidity
conditions within the building shall approximate
humidity conditions, which will prevail when the
building is occupied. Care should be taken to
maintain humidity within the range of 35% to
50%.
1.04 WARRANTY
A. Action Floor Systems, LLC. warrants the
material it ships to be free from defects in
materials and workmanship for a period of one
year and the flooring installer warrants the
installation of the flooring to be free of
defects in materials and workmanship for a
period of one year. The exclusive remedy under
this warranty shall be replacement of defective
material supplied by Action Floor Systems, LLC.
or correction of defective installation by the
flooring installer. All implied warranties of
merchantability or fitness for intended use are
limited to the period of this warranty. This
warranty excludes consequential damages.
B. This warranty does not cover damage caused by
fire, winds, floods, chemicals or other abuse or
by failure of other contractors to adhere to
specifications, or neglect of reasonable
precaution to provide adequate ventilation
during hot and humid weather. This warranty also
excludes damage due to excessive dryness or
excessive moisture from humidity, spillage,
migration through the slab or wall or any other
source. This warranty also excludes damage to
floors due to ordinary wear and tear, faulty
construction of the building, (other than the
flooring installation), separation of the
concrete slab underlying the floor, settlement
of the walls, or use of water on the floor.
C. During the warranty period, the floor cannot
be coated without the permission of the floor
contractor.
PART
2 - PRODUCTS
2.01 MATERIALS
A. Flooring
1. Flooring shall be northern hard maple strip
flooring, 25/32" x 2-1/4" (20mm x 57mm) or
25/32” x 1-1/2” (20mm x 38mm) MFMA grade marked
& stamped as manufactured by Action Floor
Systems, LLC.
2. Grades available are MFMA 1st, 2nd&Btr., 3rd&Btr.,
and 3rd grade.
3. Action Long Length Strip (LL).
B. Subfloor
1. Vapor barrier shall be 6-mil polyethylene.
2. Pads shall be AirTech 7/16" (11mm) natural
rubber pads as supplied by Action Floor Systems,
LLC. Option: AirTech III 5/8” (16mm) pads or
AirTech IV 3/4" (19mm) pads
3. Panels shall be 15/32" (12mm) thick, CD face,
exposure l, 4ply rated plywood.
4. Subfloor fasteners shall be 1" (25mm) cleats
or 16-gauge staples.
5. Flooring nails shall be 2" (50mm) cleats or
staples.
6. Wall base shall be 4" x 3" (76mm x 102mm)
vented cove base with premolded corners (specify
black or brown), as supplied by Action Floor
Systems, LLC.
PART
3 - EXECUTION
3.01 INSPECTION
A. Inspect concrete slab for proper tolerance
and dryness reporting any discrepancies in
writing to the general contractor.
B. All work to put the concrete slab in
acceptable condition shall be the responsibility
of the general contractor.
3.02 INSTALLATION
A. Cover concrete slab with poly lapping edges
6" (150mm) and seal.
B. Action AirTech pads shall be attached to the
underside of the first layer of plywood 12"
(300mm) o.c. 32 pads per 4' x 8' (1.2m x 2.4m)
sheet.
C. Place the first layer of plywood diagonal to
the intended direction of the finish flooring,
allow 1/4” (6mm) spacing at all edges.
D. Lay the second layer of plywood without pads
at the opposite 45-degree angle to the first
layer. No joints in the second layer shall
coincide with a joint in the first layer. Fasten
layers together with 1" (25mm) coated staples or
nails, starting from the center of the sheet
working outward fasten approximately 12” o.c.
(300mm), minimum of 32 fasteners per panel.
Allow 1/4" (6mm) between panel edges, and a 2"
(50mm) expansion void at walls and vertical
obstructions.
E. Machine nail strip flooring into second layer
of plywood parallel to the long dimension of the
area. Provide adequate expansion at regular
intervals across the floor during installation
as dictated by the average humidity conditions
of the area according to the recommendations of
the local Action Floor Systems, LLC. flooring
contractor. Provide 2" (50mm) expansion voids at
perimeters and all vertical obstructions.
3.03 FLOOR SANDING
A. Use coarse, medium and fine grade sandpaper.
B. After sanding with drum sander, buff entire
floor using 100 grit screenback or equal grit
sandpaper, with a heavy-duty buffing machine.
C. Vacuum or tack floor before first coat of
finish.
D. Floor shall present a smooth surface without
drum stop marks, gouges, streaks or shiners.
3.04 FINISHING
A. Inspect entire area of floor to ensure that
the surface is acceptable for finishing,
completely free from sanding dust and perfectly
clean.
B. Apply seal and finish per manufacturer's
instructions.
C. Screenback or steel wool and vacuum or tack
between each coat after it dries.
D. Apply game lines accurately after the seal
coat, after buffing and vacuuming. Lay out in
accordance with drawings. For game lines, use
current rules of association having
jurisdiction. Lines shall be straight with sharp
edges in colors selected by the architect.
3.05 BASE INSTALLATION
A. Affix rubber base to wall with recommended
adhesive or screws. Miter all corners carefully.
Use premolded outside corners. Install aluminum
thresholds as required, anchoring firmly in
concrete floor beyond limits of wood flooring.
3.06 CLEAN UP
A. Clean up all unused materials and debris and
remove from premises.
3.07 MAINTENANCE
A. Upon completion of floor installation, the
owners attendants or individuals in charge and
responsible for the upkeep of the building are
to see that the care and maintenance
instructions of the MFMA are followed. Failure
to do so may void warranty.
01/09
IT IS THE POLICY OF ACTION FLOOR SYSTEMS, LLC.
TO CONTINUOUSLY UPDATE AND IMPROVE OUR PRODUCT
LINES. THEREFORE, WE RESERVE THE RIGHT TO
CHANGE, MODIFY OR DISCONTINUE SYSTEMS,
SPECIFICATIONS AND ACCESSORIES OF ALL PRODUCTS
AT ANY TIME WITHOUT ANY NOTICE OR OBLIGATION TO
ANY PURCHASERS.
|